The site plan engine

IntelliCascade™, the site optimisation, and the final check every placed footing passes through.

Site Plan runs IntelliCascade™, CivilTech Studio’s engine for designing the footings of a whole plot together. It works through the columns and footing types, places each footing within the boundary, and merges or reshapes footings that would clash.

Placement alone isn’t proof. A footing designed centred on its column and then pushed inward by the boundary carries the load off-centre; a footing that fits on its own may run into its neighbour. So every footing the optimiser places is checked again where it ends up, by the same engine as a single footing, with the column’s real offset and the bars the schedule actually gives it.

A footing pushed inward by the boundary is off-centre, so it is checked again where it ends up.

When a placed footing fails

The final check tries remedies in order, keeping the first that passes:

  1. Redesign the bars and depth in place, when the soil and stability checks already pass.
  2. Strap the footing to a standing neighbour, or to the edge column facing it across the plot.
  3. Refit the footing, centred, within the room it has.
  4. Combine it with its neighbour into one footing.
  5. Join nearby failing columns on a local mat.

No two passing footings may overlap. A remedy that would run into a standing footing is refused. Anything still failing is reported with its reason and the remedy that would be needed; if even a mat over the whole plot exceeds the bearing capacity, you are told no shallow foundation works and piles should be considered.

Something missing or wrong? Tell us from the changelog page or the feedback button.