Bill of quantities
One row per element. Quantity multiplies the volume.
Plaster
Cement : sand plaster by the dry-volume method. Area × thickness × dry factor, plus wastage.
Material rates
Currently using region preset. Edit any cell to override locally.
Assumptions
Tune the figures the estimator used to hide.
Swaps the cement carbon factor 0.83 → 0.45 kg CO₂/kg. Cost held the same (blended cement is similarly priced).
Tip: a PPC/GGBS blend would cut ≈ 4.52 t CO₂.
- Steel₹1.39 lakh(33%)
- Cement₹95,253(22%)
- Formwork₹69,570(16%)
- Sand₹34,636(8%)
- Labour₹31,470(7%)
- Aggregate₹27,337(6%)
- Plaster labour₹25,550(6%)
- Water₹1,844(0%)
How the RCC Cost Estimator works
The estimator builds a quick bill of quantities for RCC work. Add one row per element type (slab, beam, column, footing, raft or RCC wall), choose the concrete grade (M20, M25, M30 or M40), and enter the volume of one element and how many there are. Each row is priced and the rows are added up into one total.
Each grade has fixed per-m³ quantities of cement, sand, 20 mm aggregate and water. These are indicative design-mix proportions for OPC 43, kept within the IS 456 limits on water-cement ratio and cement content; they are not a mix design. Steel is taken as a typical site average for the element type, from 75 kg/m³ for footings to 220 kg/m³ for columns. The wastage allowance (4% by default, 0 to 10%) is added to the concrete materials only: cement, sand, aggregate and water. Steel, formwork and labour are priced on the net volume of the members, because wasted concrete is never reinforced, shuttered or placed. Formwork uses a typical ratio for each element (slab 8, beam 9, column 10, RCC wall 10, footing 2.5 and raft 0.5 m² per m³) unless you enter one ratio for every row.
Rates come from region presets (Tier-2 default, Mumbai, Delhi NCR, Bangalore, Chennai) and every rate can be edited. They are indicative, so replace them with current local quotations. The tool also reports embodied carbon in tonnes of CO₂-e, with a low-carbon option that swaps OPC for a PPC/GGBS blend, and it can export the BOQ to PDF or show it in US dollars.
- Concrete volume incl. wastage
- V = volume × quantity × (1 + wastage/100)
- Materials
- cement bags, sand m³, aggregate m³, water L = V × per-m³ quantity for the grade
- Steel
- steel (kg) = volume × quantity × kg/m³ for the element type (no wastage)
- Formwork
- formwork (m²) = volume × quantity × formwork ratio (the element’s own, or your override)
- Labour
- labour = volume × quantity × labour rate per m³
- Row cost
- cost = Σ (quantity × rate) for cement, sand, aggregate, water, steel, formwork and labour
- Embodied carbon
- CO₂ = cement kg × 0.83 (0.45 blended) + sand kg × 0.005 + aggregate kg × 0.012 + steel kg × 1.85 + water L × 0.0003
Follows: IS 456:2000 Table 5 (maximum w/c 0.55 for RCC, mild exposure) · IS 456:2000 Cl 8.2.4.2 (cement content not more than 450 kg/m³) · IS 10262:2019 Table 4 (186 L water per m³ for 20 mm aggregate)
Worked example: cost of a 10 m³ M25 slab at the default Tier-2 rates
Given
- Element: slab (80 kg/m³ steel), grade M25, volume 10 m³, quantity 1
- Wastage 4%, formwork ratio set to 2.5 m²/m³ (the slab default is 8)
- Indicative Tier-2 rates: cement ₹400/bag, sand ₹1,800/m³, aggregate ₹1,500/m³, water ₹0.05/L, steel ₹65/kg, formwork ₹450/m², labour ₹1,500/m³
Steps
- Concrete incl. wastage: V = 10 × 1 × 1.04 = 10.4 m³.
- Cement: 10.4 × 8.0 = 83.2 bags × ₹400 = ₹33,280.
- Sand: 10.4 × 0.42 = 4.368 m³ × ₹1,800 = ₹7,862.
- Aggregate: 10.4 × 0.84 = 8.736 m³ × ₹1,500 = ₹13,104.
- Water: 10.4 × 186 = 1,934.4 L × ₹0.05 = ₹96.72.
- Steel: 10 × 80 = 800 kg × ₹65 = ₹52,000 (no wastage on steel).
- Formwork: 10 × 2.5 = 25 m² × ₹450 = ₹11,250 (no wastage on formwork).
- Labour: 10 m³ × ₹1,500 = ₹15,000 (no wastage on labour).
- Total: 33,280 + 7,862.40 + 13,104 + 96.72 + 52,000 + 11,250 + 15,000 = ₹1,32,593.12, shown as ₹1.33 L; per m³ of concrete bought, 1,32,593.12 / 10.4 = ₹12,749.
Result: About ₹1.33 lakh for the slab (₹12,749 per m³), with steel the largest item at ₹52,000 and 5.13 t CO₂-e embodied carbon. With the slab’s own formwork ratio of 8 m²/m³ instead of 2.5, formwork is 80 m² (₹36,000) and the total about ₹1.57 lakh.
Enter the same values in the calculator above to check each step.
Frequently asked questions
What is the cost of 1 cubic metre of RCC in India?
It depends on the grade, the steel content and local rates. At this tool's indicative Tier-2 rates, 1 m³ of M25 slab with 80 kg of steel, 2.5 m² of formwork and labour comes to about ₹13,051 before wastage (about ₹15,526 with the slab’s default 8 m² of formwork). Steel (₹5,200) and cement (₹3,200) make up about 64% of that, so check those two rates against current local prices first.
How many bags of cement are required for 1 m³ of M20 and M25 concrete?
The estimator uses 6.8 bags for M20, 8.0 for M25, 8.6 for M30 and 9.0 for M40, per m³ of placed concrete with 50 kg bags. These are indicative design-mix figures within the IS 456 limits, not the IS 456 Table 9 nominal mixes, so an actual mix design can give a different cement content.
How much steel is required per cubic metre of RCC?
The tool uses typical site averages: slab 80 kg/m³, footing 75, RCC wall 90, raft 110, beam 130 and column 220 kg/m³. These are for budgeting only, not code minimums. The actual steel depends on the design of each member.
How is wastage added in a concrete cost estimate?
The wastage percentage, 4% by default, increases the concrete volume used for the cement, sand, aggregate and water quantities. It is not added to steel, formwork or labour, because concrete that is wasted is never reinforced, shuttered or placed. For a 10 m³ slab, 4% wastage means materials are bought for 10.4 m³.
What does the RCC cost estimator not include?
It prices only the RCC itself: concrete materials, reinforcement, formwork and labour. It does not include excavation, PCC, masonry, finishes, plant hire, transport, contractor overheads, profit or taxes. It also does not design the mix or check reinforcement, and the rates are indicative defaults that you should replace with site quotations.
Step-by-step guides
- Cement, Sand and Aggregate for 1 m³ Concrete: M20 and M25 QuantitiesHow many bags of cement and how much sand and aggregate go into 1 m³ of M20 or M25 concrete: the 1.54 dry volume method compared with a design-mix table.
- Earthwork Calculation: Prismoidal vs Average End Area (Worked Example)Work out cutting and filling volumes from cross-sections by the average end area and prismoidal methods, with bulking, shrinkage and a 100 m road example.
- Steel Weight Formula D²/162: Rebar Weight per Metre with TableHow to calculate the weight of a steel bar with D²/162: where 162 comes from, a kg/m table for 6 to 40 mm bars, and worked examples for 12 mm bars.
- Septic Tank Design (IS 2470) — Size & DimensionsSeptic tank design calculation as per IS 2470 (Part 1): sewage flow, detention, digestion and sludge volumes, Table 5/6 minimum sizes and L × B × depth, worked through for a 10-user house with a size table for 5 to 150 users.
Related tools
- Concrete Mix DesignGet grade-specific cement, sand and aggregate quantities from a proper mix design.
- Section DesignFind the actual steel needed in a beam or column instead of a typical ratio.
- Steel Weight CalculatorConvert bar sizes and lengths into kilograms of steel.
- RC Building EstimatorTake off concrete and bar-bending quantities for a whole building.