RCC Cost Estimator

BOQ & rate analysis

Region
4.0%

Bill of quantities

One row per element. Quantity multiplies the volume.

12.48 m³ total₹1.89 lakh
2.81 m³ total₹52,473
2.58 m³ total₹64,192
3.95 m³ total₹49,150

Plaster

Cement : sand plaster by the dry-volume method. Area × thickness × dry factor, plus wastage.

26.1 bags · 5.43 m³ sand · 783 L water₹34,954
27.4 bags · 3.80 m³ sand · 822 L water₹24,458
8.6 bags · 0.89 m³ sand · 257 L water₹10,554

Material rates

Currently using region preset. Edit any cell to override locally.

Assumptions

Tune the figures the estimator used to hide.

Swaps the cement carbon factor 0.83 → 0.45 kg CO₂/kg. Cost held the same (blended cement is similarly priced).

Formwork ratio override (m² per m³, 0 = per element)
USD rate (₹ per $)
Plaster dry-volume factor (wet × factor)
Plaster mixing water (× cement mass)
Plaster labour (₹ per m²)
Curing water (L per m² per day, 7 days — IS 456 Cl 13.5.1)
Estimated total
₹4.25 lakh
₹4,24,864
21.82 m³ · ₹19,472 per m³ · 4.0% wastage included
14.34 t CO₂-eembodied carbon

Tip: a PPC/GGBS blend would cut ≈ 4.52 t CO₂.

Cost composition
  • Steel₹1.39 lakh(33%)
  • Cement₹95,253(22%)
  • Formwork₹69,570(16%)
  • Sand₹34,636(8%)
  • Labour₹31,470(7%)
  • Aggregate₹27,337(6%)
  • Plaster labour₹25,550(6%)
  • Water₹1,844(0%)
Water
Mixing water — concrete4,058 L
Mixing water — plaster1,861 L
Curing — concrete faces (155 m², 7 days)5,411 L
Curing — plaster (7 days)25,550 L
Total water36.9 kL
Educational disclaimer: mix proportions are indicative design mixes held inside the IS 456 w/c and cement limits, not a mix design; steel ratios are typical site averages, not code minimums. Use the Concrete Mix Design module for grade-specific BOQ and the Section Design module for accurate steel demand on a specific section.

How the RCC Cost Estimator works

The estimator builds a quick bill of quantities for RCC work. Add one row per element type (slab, beam, column, footing, raft or RCC wall), choose the concrete grade (M20, M25, M30 or M40), and enter the volume of one element and how many there are. Each row is priced and the rows are added up into one total.

Each grade has fixed per-m³ quantities of cement, sand, 20 mm aggregate and water. These are indicative design-mix proportions for OPC 43, kept within the IS 456 limits on water-cement ratio and cement content; they are not a mix design. Steel is taken as a typical site average for the element type, from 75 kg/m³ for footings to 220 kg/m³ for columns. The wastage allowance (4% by default, 0 to 10%) is added to the concrete materials only: cement, sand, aggregate and water. Steel, formwork and labour are priced on the net volume of the members, because wasted concrete is never reinforced, shuttered or placed. Formwork uses a typical ratio for each element (slab 8, beam 9, column 10, RCC wall 10, footing 2.5 and raft 0.5 m² per m³) unless you enter one ratio for every row.

Rates come from region presets (Tier-2 default, Mumbai, Delhi NCR, Bangalore, Chennai) and every rate can be edited. They are indicative, so replace them with current local quotations. The tool also reports embodied carbon in tonnes of CO₂-e, with a low-carbon option that swaps OPC for a PPC/GGBS blend, and it can export the BOQ to PDF or show it in US dollars.

Concrete volume incl. wastage
V = volume × quantity × (1 + wastage/100)
Materials
cement bags, sand m³, aggregate m³, water L = V × per-m³ quantity for the grade
Steel
steel (kg) = volume × quantity × kg/m³ for the element type (no wastage)
Formwork
formwork (m²) = volume × quantity × formwork ratio (the element’s own, or your override)
Labour
labour = volume × quantity × labour rate per m³
Row cost
cost = Σ (quantity × rate) for cement, sand, aggregate, water, steel, formwork and labour
Embodied carbon
CO₂ = cement kg × 0.83 (0.45 blended) + sand kg × 0.005 + aggregate kg × 0.012 + steel kg × 1.85 + water L × 0.0003

Follows: IS 456:2000 Table 5 (maximum w/c 0.55 for RCC, mild exposure) · IS 456:2000 Cl 8.2.4.2 (cement content not more than 450 kg/m³) · IS 10262:2019 Table 4 (186 L water per m³ for 20 mm aggregate)

Worked example: cost of a 10 m³ M25 slab at the default Tier-2 rates

Given

  • Element: slab (80 kg/m³ steel), grade M25, volume 10 m³, quantity 1
  • Wastage 4%, formwork ratio set to 2.5 m²/m³ (the slab default is 8)
  • Indicative Tier-2 rates: cement ₹400/bag, sand ₹1,800/m³, aggregate ₹1,500/m³, water ₹0.05/L, steel ₹65/kg, formwork ₹450/m², labour ₹1,500/m³

Steps

  1. Concrete incl. wastage: V = 10 × 1 × 1.04 = 10.4 m³.
  2. Cement: 10.4 × 8.0 = 83.2 bags × ₹400 = ₹33,280.
  3. Sand: 10.4 × 0.42 = 4.368 m³ × ₹1,800 = ₹7,862.
  4. Aggregate: 10.4 × 0.84 = 8.736 m³ × ₹1,500 = ₹13,104.
  5. Water: 10.4 × 186 = 1,934.4 L × ₹0.05 = ₹96.72.
  6. Steel: 10 × 80 = 800 kg × ₹65 = ₹52,000 (no wastage on steel).
  7. Formwork: 10 × 2.5 = 25 m² × ₹450 = ₹11,250 (no wastage on formwork).
  8. Labour: 10 m³ × ₹1,500 = ₹15,000 (no wastage on labour).
  9. Total: 33,280 + 7,862.40 + 13,104 + 96.72 + 52,000 + 11,250 + 15,000 = ₹1,32,593.12, shown as ₹1.33 L; per m³ of concrete bought, 1,32,593.12 / 10.4 = ₹12,749.

Result: About ₹1.33 lakh for the slab (₹12,749 per m³), with steel the largest item at ₹52,000 and 5.13 t CO₂-e embodied carbon. With the slab’s own formwork ratio of 8 m²/m³ instead of 2.5, formwork is 80 m² (₹36,000) and the total about ₹1.57 lakh.

Enter the same values in the calculator above to check each step.

Frequently asked questions

What is the cost of 1 cubic metre of RCC in India?

It depends on the grade, the steel content and local rates. At this tool's indicative Tier-2 rates, 1 m³ of M25 slab with 80 kg of steel, 2.5 m² of formwork and labour comes to about ₹13,051 before wastage (about ₹15,526 with the slab’s default 8 m² of formwork). Steel (₹5,200) and cement (₹3,200) make up about 64% of that, so check those two rates against current local prices first.

How many bags of cement are required for 1 m³ of M20 and M25 concrete?

The estimator uses 6.8 bags for M20, 8.0 for M25, 8.6 for M30 and 9.0 for M40, per m³ of placed concrete with 50 kg bags. These are indicative design-mix figures within the IS 456 limits, not the IS 456 Table 9 nominal mixes, so an actual mix design can give a different cement content.

How much steel is required per cubic metre of RCC?

The tool uses typical site averages: slab 80 kg/m³, footing 75, RCC wall 90, raft 110, beam 130 and column 220 kg/m³. These are for budgeting only, not code minimums. The actual steel depends on the design of each member.

How is wastage added in a concrete cost estimate?

The wastage percentage, 4% by default, increases the concrete volume used for the cement, sand, aggregate and water quantities. It is not added to steel, formwork or labour, because concrete that is wasted is never reinforced, shuttered or placed. For a 10 m³ slab, 4% wastage means materials are bought for 10.4 m³.

What does the RCC cost estimator not include?

It prices only the RCC itself: concrete materials, reinforcement, formwork and labour. It does not include excavation, PCC, masonry, finishes, plant hire, transport, contractor overheads, profit or taxes. It also does not design the mix or check reinforcement, and the rates are indicative defaults that you should replace with site quotations.

Step-by-step guides